Project Timeline

The Open Source Secure Element (OSSE) project is planned as a 6-month feasibility study and prototype development phase. This section outlines the project timeline and key milestones.

Project Duration

  • Total Duration: 6 months
  • Start Date: Upon funding approval
  • End Date: 6 months after project initiation

Key Milestones

  1. Month 1: Completion of the feasibility study
    • Analysis of the OpenTitan framework
    • Design of the blockchain-based supply chain documentation system
    • Evaluation of security features and their integration with Ethereum standards
  2. Month 2-3: Development environment setup
    • Configuration of the CW340 Luna FPGA board
    • Implementation of basic secure element functionality
    • Setup of development and testing environments
  3. Month 4-5: Prototype development
    • Implementation of secure key generation
    • Development of transaction signing capabilities
    • Integration of encrypted key storage
  4. Month 6: Testing and documentation
    • Security testing and validation
    • Documentation of the prototype
    • Preparation of the final report and blueprint for serial production

Deliverables

  1. Feasibility Study Report: Comprehensive analysis of the OpenTitan framework and its suitability for the hardware wallet
  2. Functional Prototype: Working prototype on the CW340 Luna FPGA board with basic hardware wallet functionality
  3. Technical Documentation: Detailed documentation of the prototype’s design and implementation
  4. Blueprint for Serial Production: Guidelines and specifications for the serial production of the secure element