Project Timeline
The Open Source Secure Element (OSSE) project is planned as a 6-month feasibility study and prototype development phase. This section outlines the project timeline and key milestones.
Project Duration
- Total Duration: 6 months
- Start Date: Upon funding approval
- End Date: 6 months after project initiation
Key Milestones
- Month 1: Completion of the feasibility study
- Analysis of the OpenTitan framework
- Design of the blockchain-based supply chain documentation system
- Evaluation of security features and their integration with Ethereum standards
- Month 2-3: Development environment setup
- Configuration of the CW340 Luna FPGA board
- Implementation of basic secure element functionality
- Setup of development and testing environments
- Month 4-5: Prototype development
- Implementation of secure key generation
- Development of transaction signing capabilities
- Integration of encrypted key storage
- Month 6: Testing and documentation
- Security testing and validation
- Documentation of the prototype
- Preparation of the final report and blueprint for serial production
Deliverables
- Feasibility Study Report: Comprehensive analysis of the OpenTitan framework and its suitability for the hardware wallet
- Functional Prototype: Working prototype on the CW340 Luna FPGA board with basic hardware wallet functionality
- Technical Documentation: Detailed documentation of the prototype’s design and implementation
- Blueprint for Serial Production: Guidelines and specifications for the serial production of the secure element